Interconnection agreement: what an executed LGIA commits

TL;DR

An interconnection agreement is the executed contract between an interconnecting customer and the party that owns the network it is connecting to. It is the last rung of the power-document ladder and the first one that creates obligations rather than expectations: it allocates the scope and cost of the interconnection facilities and network upgrades, sets milestones and the security that backs them, and states what each side must do and by when. What it does not do is deliver electricity on a date — construction still has to happen — and what a lender reads in it is mostly the size of the obligations it puts on the customer, not the rights it gives them.

Defining the term

An interconnection agreement is the executed contract between an interconnecting customer and the party responsible for the network it connects to — a transmission owner, a distribution utility, or a regional system operator, depending on the market and the voltage.

The document class carries different names in different places. In much of the United States the generation-side form is a large-generator interconnection agreement, commonly written LGIA, with small-generator and load-side equivalents alongside it; elsewhere the equivalent instrument sits inside a connection agreement or a grid access contract. The names are not interchangeable and the forms are not identical. What is common across all of them is the job the document does, which is the only durable thing to write down: it converts a studied position into allocated obligations between named parties.

That is what distinguishes it from everything below it on the ladder. A will-serve letter records an expectation. A completed study produces a number. An executed agreement produces a party who must build something and a party who must pay for it. The distinction is not one of degree — it is the point at which the power position stops being diligence and starts being contract.

Two qualifications belong in the definition rather than in a footnote, because both are load-bearing.

It is not a power supply contract. An interconnection agreement governs the connection — the physical and contractual arrangements by which the site attaches to the network. What electricity costs, who supplies it and on what terms is a separate arrangement under a tariff or a supply contract. A project holding an executed interconnection agreement and no supply arrangement has a door and nothing coming through it.

It is not a delivery date. The agreement allocates who constructs the interconnection facilities and the network upgrades. Construction then has to happen, on a schedule controlled by whoever is obligated to perform it, and the gap between execution and energization is where projects most often lose time they had already committed elsewhere.

LGIA versus a large-load or electric-service agreement

An LGIA is a generation-side agreement: it is used for a generating facility connecting so that electricity can be injected into the network. A data center is principally a load seeking to take electricity from the network. Its binding paper may instead be called a large-load interconnection agreement, electric-service agreement, facilities agreement, construction agreement, connection agreement, or a combination of documents under the utility's tariff. The label and document stack differ by market, utility, voltage and project configuration.

That distinction matters because generation and load can impose different studies, facilities, operating limits and payment obligations. It matters even more when a data-center campus includes on-site generation or storage. The campus may then have one set of documents for serving the load and another for interconnecting equipment that can operate in parallel with, or export to, the network. Holding a generation-side agreement does not by itself establish the amount, firmness or timing of electric service available to the load.

For underwriting, the correct response to unfamiliar terminology is not to force the document into an LGIA template. It is to identify the operative agreements and follow the obligations across them. A short electric-service agreement may incorporate a tariff, a facilities exhibit, a construction schedule and separate credit-support terms; the commercially important provisions may therefore sit outside the signature document.

QuestionGeneration-side paper such as an LGIALoad-side paper for a data center
What is connectingA generating facility that may inject powerA customer facility taking service, sometimes with generation or storage alongside it
Common labelsLGIA or another generator interconnection formLarge-load, electric-service, facilities, construction or connection agreement, depending on the market
Core physical questionWhat facilities and upgrades permit the generator to interconnect and operateWhat facilities and upgrades permit the utility or network to serve the requested load
Credit focusUpgrade cost, milestones, security, operating limits and transferService capacity, firmness, energization conditions, facilities cost, deposits, operating limits and transfer
What it does not proveThat a separate data-center load has firm serviceThat generation equipment may export or operate in parallel without separate approval

The document stack a reviewer should request

The signed agreement rarely contains the whole commercial position. It may incorporate a tariff by reference, attach an earlier facilities study, leave the construction schedule in a later exhibit, and place deposits or credit support in separate instruments. Amendments and utility correspondence can also change the dates or scope without restating the original document. Reviewing only the signature agreement is therefore capable of producing a precise answer to the wrong version of the transaction.

The need to identify the operative stack is heightened by a moving large-load rule set. In June 2026 FERC directed all six regional grid operators under its jurisdiction to justify or reform the tariff rules governing how data centers and other large loads connect to the transmission system. (Federal Energy Regulatory Commission, as of September 18, 2026) That action does not create one national large-load agreement, and it should not be read as one. It is evidence that the governing process and document labels remain market-specific and subject to change. The reviewer has to establish which tariff, procedure and form applied when the position was created, and whether a later amendment or transition rule affects it.

A complete request follows the obligation rather than the filename. The facilities scope should reconcile to the latest studies and engineering exhibits. The current schedule should reconcile to milestone notices and utility correspondence. Cost responsibility should reconcile to invoices, deposits, security and contribution agreements. Service capacity and operating limits should reconcile to the tariff and electric-service paper. Assignment should reconcile to any consent already obtained and to change-of-control language across the stack.

The practical output is a one-page obligations schedule naming each requirement, the document and clause that creates it, the responsible party, the due date, the amount or capacity, and evidence of current compliance. That schedule is more useful to capital than a folder marked "executed interconnection agreement" because it shows whether the position is alive today and what has to be funded to keep it alive tomorrow.

RequestWhat it should establishMismatch to flag
Executed agreement and amendmentsNamed parties, scope, term, default and transferMarketing summary relies on a superseded version
Studies and facilities exhibitsRequested capacity, point of connection and required workCurrent site design differs from the studied configuration
Tariff and service documentsFirmness, billing demand, curtailment and supply termsConnection rights are presented as firm energy supply
Construction schedule and noticesCurrent milestones, dependencies and long-stop datesOriginal target date is used after the schedule moved
Invoices, deposits and securityAmounts paid, amounts due and refund or draw conditionsBudget carries a study estimate instead of current exposure
Status correspondence and consentsCompliance, delay, waiver, assignment and change of controlSilence is treated as approval or consent

What the agreement allocates

Reduced to its structure, the document assigns each of the items below to somebody. The value of reading it as a finance document rather than a technical one is that every row is a cost, a timing exposure, or a credit requirement wearing engineering vocabulary.

What is allocatedThe question it answersWhy it matters to the credit
Interconnection facilitiesWhat is built at and around the point of connection, and by whomScope the customer usually pays for whether or not it owns the result
Network upgradesWhat has to be reinforced beyond the point of connectionThe largest and least predictable number in the whole power budget
Cost responsibilityWho funds each element, and whether any of it is refundable or reimbursableDecides whether the upgrade cost is a capital item, a deposit, or a permanent loss
MilestonesWhat the customer must achieve, by when, to keep the agreement aliveMissed milestones can terminate the agreement without any dispute about the merits
Security and credit supportWhat must be posted, in what form, by which entity, and when it steps upA funded obligation that competes with the project's other uses of capital
Operating obligationsHow the facility must behave once connected, including any interruption rightsConstrains what availability the facility can promise a tenant — see curtailment
Term, default and terminationHow long it runs, what breaches it, and what survivesDetermines whether the position outlives a delay or dies during one
Assignment and change of controlWho may take the agreement over, and whose consent that needsDecides whether the position can be moved into a financeable structure at all

What a lender reads in it

A first-time reader looks for the megawatts. A credit reader looks for the obligations, because the rights in this document are largely fixed and the obligations are where the project can fail.

The upgrade cost, and whether it is capped. Network upgrade obligations are the item most capable of moving a project from viable to not. What matters is not the estimate but its status: whether the number is a study output or a contractual figure, whether it can be revised, what triggers a revision, and whether anything reimburses the customer for work that benefits the wider network. An uncapped, revisable upgrade obligation is an open position on the wrong side of the balance sheet, and it is often the single largest one in a layer-1 budget.

The security package running the other way. The customer typically posts security to the network party, escalating as the work proceeds. That is capital committed to a counterparty that is not financing the project, on a schedule the project does not control, and it has to be funded from somewhere before anything is earning. Where the posting entity is thinly capitalised, support has to come from a parent — which quietly re-couples layers a structure was built to separate.

The milestone schedule as a termination risk. The agreement is a set of conditions the customer must keep meeting. Positions are lost to unmet deposits and unmet milestone dates far more often than to substantive disagreements, and a delay elsewhere in the project can cascade into a default here — which is why the milestone dates belong in the same schedule as the construction programme rather than in a separate file.

Assignment and change of control. The security package over a power position is generally indirect: capital secures the entity that holds the agreement rather than the agreement itself. That works only where a change in the entity's ownership is not treated as an assignment requiring consent. It is a drafting point with an outsized commercial consequence, and it is the whole subject of who holds the interconnection position.

The operating obligations, read as availability. What the facility has committed to do when the system is constrained determines what availability it can sell. A tenant contracting for continuous operation cannot be served out of a connection the operator may reduce at its discretion — the repricing mechanism set out in curtailment.

And the description of the load or the generation. The agreement was studied and executed against a described thing. Where the project's plans change materially, the description may no longer match, and the consequences of that mismatch are specific rather than general. The questions to ask, and who has to answer them, are worked through in interconnection under a load change.

What it still does not do

An executed agreement is the strongest power document most projects will ever hold, and it is routinely oversold on the strength of that. Four things it does not settle.

It does not make the power available. Execution allocates the work; the work then has to be done. Where the network party is building the upgrades, the schedule belongs to them, and the customer's remedies for delay are whatever the agreement provides and generally no more. A project whose energization date is an assumption about somebody else's construction programme should say so out loud in its own model.

It does not fix the cost. Estimates in an executed agreement are frequently subject to true-up against actual construction cost. The direction of travel is not usually favourable, and a budget carrying the estimate as though it were the price has understated the layer-1 capital requirement by an amount nobody has sized.

It does not make the position pledgeable. The rights under it are generally restricted on assignment and encumbered with obligations, which is why direct security over the agreement is uncommon and awkward. The workable answer is security over the holder, and it has to be put in place before it is needed rather than negotiated during enforcement.

And it does not answer whether the site is financeable. The power position is one gate of several. Site control has to outlast the timeline, entitlement has to permit the use, and the demand behind the megawatts has to be contracted rather than indicated. The full set is in what makes a site financeable, and a genuine, executed, well-negotiated interconnection agreement clears exactly one of them.

The useful summary for a buyer, a broker or a lender's analyst reading a data room: an executed interconnection agreement moves the power question from *whether* to *how much and by when*. That is a large move. It is not the end of the diligence, and the paragraph in the marketing pack describing it as "fully powered" is describing something the document does not say.

Frequently asked

What is an interconnection agreement?

It is the executed contract between an interconnecting customer and the party responsible for the network — a transmission owner, a distribution utility or a system operator. It allocates what interconnection facilities and network upgrades get built and by whom, who pays for them, what milestones and security the customer must maintain, how the facility must operate once connected, and who may take the agreement over. It is the first document on the power ladder that creates obligations rather than expectations.

What is an LGIA?

LGIA stands for large-generator interconnection agreement — the common United States name for the generation-side form of the document, with small-generator and load-side equivalents alongside it. Other markets use other names and other forms, and the content is not identical between them. Treating LGIA as the name of a document class rather than a universal standard is the safe reading: what travels across markets is the job the agreement does, not its clauses.

Does a data center use an LGIA or a large-load interconnection agreement?

A data center taking power is a load, so its service is usually governed by load-side or electric-service documents rather than an LGIA alone. The actual names vary: a utility may use a large-load interconnection agreement, electric-service agreement, facilities agreement, construction agreement, tariff documents, or several of them together. If the campus also has generation or storage, separate generator-side approval may apply. Underwriting should therefore follow the capacity, cost, milestone, security and operating obligations across the full document set instead of assuming one label is universal.

Does an executed interconnection agreement mean the site has power?

No, and this is the most consequential misreading of the document. It means the construction of the interconnection and the required network upgrades has been scoped, allocated and costed between named parties. The work still has to be performed, generally on a schedule the customer does not control, and the interval between execution and energization is where committed timelines are most often lost. It converts an expectation into obligations; it does not convert obligations into electricity.

Who pays for the network upgrades?

That is precisely what the agreement decides, and the answer differs by market, by voltage and by the nature of the request. What is durable is the set of questions: whether the figure is a contractual number or a revisable estimate, what triggers a revision, whether any part of the customer's contribution is refundable or reimbursable over time, and what security has to be posted against the obligation in the meantime. An uncapped and revisable upgrade obligation is usually the largest open item in a layer-1 budget.

Can an interconnection agreement be assigned to a buyer?

Usually only with consent, and consent is a process rather than a formality. Some agreements are non-transferable; others permit transfer only alongside the site, or only to a party meeting stated creditworthiness tests, or only with a re-study — which resets the thing that made the position valuable. A change of control can be treated as an assignment even where the named holder never changes, which is why the point is read at the outset rather than assumed to work.

What is the difference between an interconnection agreement and a power purchase agreement?

They answer different questions and a project usually needs both. The interconnection agreement governs the connection to the network: what gets built, by whom, at whose cost, and how the facility must behave once connected. A power purchase agreement governs the commodity: who supplies electricity, in what volume, at what price, over what term. Holding one without the other is common and it is a gap — a connection with nothing contracted to flow through it, or contracted electricity with no way to take delivery.

Is a facilities agreement the same as an electric-service agreement?

Not necessarily. A facilities agreement commonly addresses the equipment and construction required to connect or serve the customer, while an electric-service agreement commonly addresses the capacity and terms on which service will be provided. A utility may combine those subjects, split them across several contracts, or incorporate key terms from its tariff. The reliable approach is to follow scope, cost, capacity, milestones and operating rights across the full document set rather than infer them from either title.

Considering a site, a power position, or the capital behind it? Speak with our team.

Submit a deal

Last updated

Continuum Capital is not a bank, not a broker-dealer, and not a direct lender. It acts as arranger and advisor: it structures and arranges capital, does not execute securities transactions, and does not hold client funds. This page is informational and is neither an offer to sell nor a solicitation of an offer to buy any security, nor a commitment to provide financing.